|
Online edition of India's National Newspaper Monday, March 26, 2001 |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Entertainment |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home |
|
Southern States
| Previous
| Next
Sothuparai reservoir nearing completion
By T. Ramakrishnan
PERIYAKULAM, MARCH 25. The Sothuparai reservoir project in Theni
district, a two-decade-old scheme, will be completed shortly.
``The deadline is April 20 but we are confident of completing the
work by March 31'', say PWD officials at the dam site.
Originally proposed in the early 1980s, the scheme got embroiled
in a number of problems and as a result, it came to a halt.
Now, thanks to the World Bank-assisted Water Resources
Consolidation Project (WRCP), it has secured a fresh lease of
life.
However, this has resulted in substantial cost escalation. When
the Government sanctioned the project in 1982, the cost was Rs.
8.7 crores. In 1997, when it was revived, the cost went up to
nearly Rs. 25 crores.
Located 12 km west of Periyakulam, the Sothuparai reservoir is so
called because of the peculiar characteristics of boulders in the
area. They are so evenly shaped that people have found it
convenient to take food on them.
The source of this storage point is Varahanathi, a tributary of
the Vaigai. Originating from the Palani Hills, Varahanathi
traverses 28 km and confluences with the Vaigai three to four km
downstream of the Vaigai dam.
A visit to the dam site reveals that the work on the last metre
of the reservoir wall is going on feverishly and massive cranes
are deployed for giving final touches to the dam. ``As per the
prescriptions of the World Bank, we are carrying out all the
measures aimed at protecting the structure of the dam and making
it less vulnerable to tremors''.
Explaining the delay, the authorities say the nature of
geological formation in the dam site was a major factor.
``Against the estimation of prevalence of hard rock boulders to
the extent of 10 per cent, we found that it was actually 60 per
cent''. The presence of more hard rock boulders led to the delay
in excavation and the department terminated the contract, leading
to litigation. All these and other problems were thrashed out
after a considerable passage of time.
The reservoir, on completion, will stabilise farming activity on
about 1,800 acres and lead to an additional command area of
nearly 1,000 acres. A new lined canal for about 7 km is being
laid. Apart from irrigation, the reservoir will be used for
providing drinking water to Periyakulam and wayside habitations
and it has been planned to draw 15 cusecs water for this purpose.
A cross-section of farmers, whose lands were acquired by the
Government for constructing the reservoir, said the affected
persons did not face problems in getting compensation. ``We are
satisfied with the way the relief-distribution mechanism was
carried out''. However, the ryots want the Government to
implement a soft-loan scheme, aimed at employment generation, for
their dependents.
Send this article to Friends by E-Mail
|
|
Section : Southern States Previous : Governor, CM extend Ugadi greetings Next : Residents confront with tanker lorry drivers | |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Entertainment |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home | |
|
Copyrights © 2001 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|