|
Online edition of India's National Newspaper Saturday, December 02, 2000 |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Entertainment |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home |
|
National
| Previous
| Next
EBs impede private sector projects
By V. Jayanth
CHENNAI, DEC. 1 If many of the Independent Power Producers (IPPs)
have not been able to achieve financial closure in time and get
on with their projects, the reasons are not far to seek. Both the
Centre and the private sector hold the State Electricity Boards
(SEBs) and the State Governments responsible for the ``tardy
progress.''
The foremost problem which has unduly delayed financial closure
for power projects, despite progress on other fronts, has been
identified as the ``poor financial health'' of the SEBs, which do
not have the ``financial capability to support more than a few
projects,'' according to an assessment by the Ministry of Power.
Almost all the financial institutions seek a bankable escrow to
finance the IPPs. But the States do not have enough escrow space
to accommodate all the IPP applicants. In some cases, even the
escrowable capacity claimed by the State Governments have not
been accepted by the financial institutions. This has also
resulted in some litigation.
The delay in the finalisation of various contracts, including a
Power Purchase Agreement, fuel supply agreement and a
transportation agreement has held up some projects, while some
promoters complain that State Governments have got into the habit
of wanting to renegotiate already concluded purchase agreements.
After taking into account all these problems, the Centre came up
with a revised mega power policy in 1998, since some of the
pending proposals involved dealing with more than one State and
their SEBs. Investors preferred to deal with a single entity and
demanded ``higher comfort levels,'' resulting in delays and
difficulties. That led to the creation of the Power Trading
Corporation and then the securitisation of dues from the SEBs.
Industry sources said that the Ministry of Power drew up a
modified security mechanism as an alternative to the escrow
mechanism to provide financial comfort to the lenders and IPPs.
Consequently, financial institutions are being nudged to move
away from escrow and link IPP financing to actual milestones in
power sector reforms by each State.
These milestones include unbundling or corporatisation of the
SEBs, privatisation of distribution, tariff rationalisation,
setting up of State Electricity Regulatory Commission,
determination of supportable capacity after assessing the demand-
supply position of power, professionalisation of SEB management,
energy audits, 100 per cent metering and billing, reduction in
Transmission and distribution losses, improvement in plant
availability, renovation and modernisation of existing power
plants, payment of subsidies by the State Governments and an
action plan to clear the overdues to the Central undertakings.
The Crisis Resolution Group, headed by the Power Minister, has
been meeting regularly to review the scenario and consider follow
up action.
As a sequel to these deliberations, financial institutions and
States have been asked to shortlist private power projects which
could be taken up so that all formalities are completed quickly
and financial closure achieved at least by March 31, 2001.
About 20 IPPs have been shortlisted for this purpose, and a
majority of them have been held up on account of problems with
the escrow from State Governments. They include Ramagundam
thermal station (520 MW) in Andhra Pradesh; Maheshwar HEP and
Bina thermal plant in Madhya Pradesh; Patalganga and Bhadravati
in Maharashtra; North Chennai Stage II in Tamil Nadu; Jamnagar in
Gujarat; Rosa and Vishnuprayag in Uttar Pradesh and the Balagarh
thermal project in West Bengal.
Since 1991, 57 private power projects to generate nearly 30,000
MW were cleared. But till now, 22 projects with a capacity of
4818 MW have been commissioned and another 19 projects with a
capacity of 5296 MW are in various stages of implementation,
according to the Power Ministry.
But capacity addition from the private sector has not come up to
expectations, because of the financial bottlenecks. During the
Eighth Plan, the private sector contributed only 1430 MW against
double that target. For the Ninth Plan, a target of 17,500 MW was
set, but then reduced to just 8363 MW during the mid-term review.
Perhaps only 7,000 MW could materialise eventually, going by
present indications.
Send this article to Friends by E-Mail
|
|
Section : National Previous : 16 more Ministers in Marandi Cabinet Next : AAI upgrading facilities to meet foggy conditions | |
|
Front Page |
National |
Southern States |
Other States |
International |
Opinion |
Business |
Sport |
Entertainment |
Miscellaneous |
Features |
Classifieds |
Employment |
Index |
Home | |
|
Copyrights © 2000 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|