|
Online edition of India's National Newspaper Friday, May 19, 2000 |
|
Front Page |
National |
International |
Southern States |
Opinion |
Business |
Sport |
Entertainment |
Miscellaneous |
Features |
Other States |
Classifieds |
Employment |
Index |
Home |
|
Southern States
| Previous
| Next
Renegotiate power projects: CAG
By Our Special Correspondent
CHENNAI, MAY 18. The Comptroller and Auditor-General of India
(CAG) has suggested that the Tamil Nadu Electricity Board (TNEB)
should renegotiate some of the agreements concluded with the
private promoter of the Basin Bridge Diesel Engine Power Project
which were either not in tune with Union Government guidelines or
caused annually repetitive losses to the board.
The CAG, who has questioned the very propriety of selection of
the private promoter for the project, has also suggested to the
board to reassess its plans for additions to generation capacity
since the State is likely to face the prospect of substantially
unwanted and high-cost surplus power if all the approved projects
went on stream.
The CAG's Report (Commercial) for the year ended March 31, 1999,
tabled in the State Assembly, has found fault with the procedure
of selection of the private promoter for the Basin Bridge project
(awarded to GMR Vasavi Industries, Hyderabad). It said five out
of seven other offers in the short list for the project were
rejected by the Government ``on grounds which lacked
justification''.
Three promoters were rejected on the ground that they were either
executing projects elsewhere or could be considered for larger
projects, and two others were not considered because they were
equipment manufacturers/suppliers and might not go in for
competitive bidding in selection of equipment.
``Rejection of offers on these grounds lacked justification since
execution of other projects (by bidders) would not affect their
ability to execute this project and it was possible to ensure
that the promoters obtained equipment only after competitive
bidding. In fact, the board did not insist on the selected
promoter (GMR Vasavi) to procure equipment only after competitive
bidding, and instead accepted their explanation that the
equipment supplier was selected after discussions'', the report
said.
Even after the Centre issued instructions (June 1996) that all
power projects which had not finalised their engineering,
procurement and construction (EPC) contract should go in for
international competitive bidding (ICB), the board did not insist
on this point again with the selected promoter, though the
promoter entered into the EPC contract only in November 1996.
``Thus the board could not obtain the most competitive offers for
both the project and the equipment''.
Other points made by the CAG report in respect of the Rs. 756-
crore 196 MW Basin Bridge Project (which has already been
commissioned) are: by agreeing to a Return on Equity (ROE)
monthly on a pro-rata basis instead of annually, the TNEB
extended additional benefit of Rs. 2.66 crores per annum to the
promoter. Incorrect computation of working capital resulted in
extra interest liability of Rs. 7.15 per annum to the board.
Computation of the incentive payable with reference to equity,
instead of return on equity, resulted in extra expenditure of Rs.
20.47 crores per annum.
Fixing of a threshold limit of the Plant Load Factor (PLF) at
68.49 per cent for computation of incentive instead of an
``achievable and realistic level'' of 80 per cent would result in
a higher commitment of Rs. 16.99 crores per annum on the part of
the TNEB, the report said.
It pointed out that the incentive payable at 0.7 per cent of
return on equity for each percentage point increase in the PLF
above 68.49 per cent, in terms of the Centre's notification of
March 30, 1992, was only the maximum prescribed and could be
negotiated by SEBs to lower levels.
Computation of fuel consumption based on the norm for the Station
Heat Rate instead of on `norms or actuals whichever is less', as
subsequently clarified by the Union Government, would result in
extra expenditure of Rs. 8.56 crores per annum to the board. By
allowing creation of excess storage capacity for fuel, it would
be put to an avoidable expenditure of Rs. 18.4 crores on fuel
throughput charges. The fuel supply agreement with Hindustan
Petroleum did not also provide for pro-rata reduction of
throughput charges if it failed to supply the maximum delivery
quantity of 3.70 lakh tonnes per annum.
Send this article to Friends by E-Mail
|
|
Section : Southern States Previous : Krishna creates ripples Next : Accused questioned in wealth case | |
|
Front Page |
National |
International |
Southern States |
Opinion |
Business |
Sport |
Entertainment |
Miscellaneous |
Features |
Other States |
Classifieds |
Employment |
Index |
Home | |
|
Copyright © 2000 The Hindu Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu |
|